September 2017 |
Dedication of the new Fellowship Hall. |
August 2017 |
The stucco work is done and the scaffolding down |
July 2017 |
Closing in the main hall, center section of the building, installing windows |
May 2017 |
Second floor walls going up |
March 2017 |
Walls are started |
March 14, 2017 |
Foundation complete |
March 6, 2017 |
Placement of prayer cards in the foundation |
January 8, 2017 |
Groundbreaking for the Fellowship Hall |
April 2016 |
Received approval from Mother Center to complete construction drawings. |
June 2015 |
Received formal approval from Mother Center to commence next phases of architectural design and
permitting. |
March 31, 2015 |
Presented our project to the General Managers Group at Mother Center and received unanimous support.
|
November 23, 2014 |
Fundraising Campaign continues with presentation to congregation |
November 9, 2014 |
Architect presents final schematic design to congregation, with preliminary budget of $2.5 million
(expected to be high water mark); receives 100% approval |
November 2014 |
Schematic Design reviewed with SRF Planning & Building Dept, receives favorable comments from both
Planning & Building & Brother Vishwananda. Formal presentation to SRF Board of Directors planned for
late January 2015 |
October 2014 |
Schematic Design completed |
September 2014 |
General Contractor hired for pre-construction services--Concord |
August 2014 |
"Master Planning Weekend": The architect meets with all the user groups |
July 2014 |
"Schematic Design" process begins (determining what will be built, in what footprint it will be
built, and what the general floor plan of the building will be) |
June 2014 |
Architect hired--Paul Ladensack of CCBG Architects. |
May 2014 |
Project Manager identified: Chris Carroll |
Feb 2014 |
Received approval of SRF Management to engage an architect and contractor for schematic plan and
budget |
March 2013 |
Presented proposed process to congregation and received 98.2% support |
Summer 2012-Spring 2013 |
Expansion committee formed to reassess needs & identify new direction |
2011-2012 |
Learned 2nd Street property NOT available - Master Plan needed to be revised |
2010-2012 |
Fund drive was undertaken / approximately $1.2 million were donated to buy adjacent properties |
2010 |
SRF Management approved 5 phase Phoenix Temple Master Plan developed under Brother Ritananda
|